Road surfacing work starting 19th August

Capital surfacing works will start next week on Mull. The roads affected will be…

B8073 Killiemore (starts Wednesday 19th August for 5 days)

C46 Achnacraig (starts Wednesday 26th August for 3 days)

B8073 Mishnish Lochs (starts Monday 31st August for 3 days)

A884 Fishnish (starts Thursday 3rd Sept for 2 days)

C54 Balure (starts Monday 7th September for 1 day)

A849 Bunessan (starts Tuesday 8th September for 2 days)

Uisken Road (starts Thursday 10th September for 2 days)

Traffic management will be in place but some delays will be inevitable.

The programme is subject to change depending on weather/supply issues etc.